3 weeks ago
Mumbai Train Services Delayed After Material Falls On OHE Wire
On Monday morning, many people in Mumbai ride trains to get to work.
Some of those trains were delayed because of a problem.
Workers were building something near Mulund station.
A piece of building material fell onto the wire that gives trains electricity.
The driver of a nearby train saw it and told the control room right away.
The railway had to turn off the power to that wire to keep everyone safe.
This caused delays during the busy morning hours.
Workers fixed the problem, and trains were running again by 12:17 PM.
The railway is also taking action against the company that was doing the construction work.
There was also some sparking near Mulund because of other railway work happening in the area.
Construction material from deck work near Mulund station fell onto an overhead equipment (OHE) wire at around 11:53 AM.
The motorman of a train on the adjacent track immediately informed the control room, prompting a shutdown of the OHE.
Train services on the affected tracks were fully restored by 12:17 PM.
Central Railway initiated action against the contractor allegedly responsible for the incident.
Heavy sparking was also reported on the Down Local Line near Mulund station, linked to ongoing Mumbai Railway Vikas Corporation (MRVC) work.
- Who
- Mumbai train commuters, Central Railway CPRO Swapnil Neela, a motorman who reported the fault, and the contractor allegedly responsible.
- What
- Construction material from deck work fell onto an overhead equipment (OHE) wire, causing a technical fault and delaying train services on the Main Line.
- Where
- Near Mulund station on Central Railway's Main Line in Mumbai, Maharashtra.
- When
- Monday, August 10, 2026, at around 11:53 AM; services were restored by 12:17 PM.
- Why
- The construction material falling onto the OHE wire forced a shutdown of the overhead equipment for safety, causing the delays.
Key facts
- Railway
- Central Railway
- Incident
- Construction material fell onto overhead equipment (OHE) wire
- Location
- Near Mulund station, Mumbai, Maharashtra
- Time of incident
- Around 11:53 AM on Monday, August 10, 2026
- Services restored
- 12:17 PM
- Official statement
- CPRO Swapnil Neela confirmed the cause
- Action taken
- Action initiated against allegedly responsible contractor
- Related incident
- Heavy sparking on Down Local Line near Mulund during MRVC work
Quotes
Central Railway CPRO Swapnil Neela
Control & Project Officer of Central Railway, Mumbai
“At around 11:53 AM today, some construction material from deck work being carried out near Mulund station fell onto the OHE wire.”
freepressjournal.in