Delhi Metro Advances Central Vista Corridor With Four Stations
Delhi Metro wants to build part of a new underground route through central Delhi.
The project includes four stations and two tunnels.
The stations will be near India Gate, Baroda House, Bharat Mandapam and the War Memorial-High Court area.
Special machines called Tunnel Boring Machines will dig the tunnels.
The tunnels will connect Kartavya Bhawan station with Indraprastha station.
Contractors can submit their bids in November 2026.
The selected contractor will have 42 months to finish this contract.
The larger route is expected to help office workers and visitors reach important places in central Delhi.
DMRC invited bids for twin underground tunnels and four stations under Contract EC-04.
The stations will serve India Gate, Baroda House, Bharat Mandapam and the War Memorial-High Court area.
Shield Tunnel Boring Machines will construct the Up and Down tunnels between Kartavya Bhawan and Indraprastha stations.
The contract has a 42-month completion period and requires bid security of Rs 21.498 crore.
The broader 9.913-kilometre Central Vista Corridor is planned to have nine underground stations serving government, judicial and visitor destinations.
- Who
- The Delhi Metro Rail Corporation, with financing partly intended from a Japan International Cooperation Agency loan.
- What
- A tender for twin underground tunnels, four stations, connecting subways, and related entry and exit structures under Contract EC-04.
- Where
- Central Delhi, between Kartavya Bhawan station and Indraprastha station, with stations planned near India Gate, Baroda House, Bharat Mandapam and the War Memorial-High Court area.
- When
- The tender was announced on September 25, 2026; bids are scheduled for November 2-9, 2026, with technical bids opening on November 10.
- Why
- To improve Metro access to major government offices, judicial institutions, convention facilities and national memorials in the Central Vista area.
Key facts
- Project
- Delhi Mass Rapid Transport System Phase V(A)
- Contract
- EC-04
- Stations under tender
- Four underground stations
- Wider corridor
- 9.913 kilometres with nine underground stations
- Construction method
- Shield Tunnel Boring Machines for twin Up and Down tunnels
- Completion period
- 42 months
- Bid security
- Rs 214.98 million, or Rs 21.498 crore
- Projected daily users
- Around 60,000 office-goers and two lakh visitors