Mumbai Metro 1 Debt Deal Collapses, Longer Trains Delayed

Mumbai Metro 1 Debt Deal Collapses, Longer Trains Delayed
Debt deal for Anil Ambani’s Mumbai Metro 1 collapses, longer trains for 5 lakh riders on hold · indianexpress.com

Mumbai Metro 1 carries about five lakh people on a typical weekday.

The company that runs it owes large sums to lenders.

A deal to reduce some of its debt fell apart because one lender did not approve it.

That lender has now started a new insolvency case against the company.

The trains will keep running, but the financial trouble could make it harder to buy more coaches.

The company says it has begun trying to get 22 coaches.

Those coaches could make at least 11 trains longer, with six cars instead of four.

Commuters and campaigners say the trains are already very crowded at busy times.

The article says it is not clear when the extra coaches will arrive.

Key facts

Metro line
Versova-Ghatkopar Metro 1, Mumbai’s first Metro line, opened in 2014.
Weekday ridership
Around five lakh passengers.
Debt owed to NARCL
Rs 2,771.32 crore.
Debt owed to IIFC UK
Rs 1,745 crore.
Proposed coaches
22 additional coaches, intended to lengthen at least 11 trains from four cars to six.
Capacity per train
The company said capacity would rise from 1,178 to 1,792.
Insolvency forum
IIFC UK moved the National Company Law Tribunal to initiate fresh proceedings.

Quotes

Dhaval Shah

Co-founder of the Andheri Lokhandwala Oshiwara Citizens Association, which has campaigned for longer trains.

“An accelerated delivery schedule has been envisaged. However, progress of the procurement is contingent upon the ongoing financial restructuring and availability of funds. Timely financial support will therefore be critical to expedite procurement, commissioning and deployment of the additional capacity.”
indianexpress.com
“At peak times, the overcrowding is so bad that the situation is a stampede waiting to happen.”
indianexpress.com