NHAI Plans Rs 794-Crore Etmadpur-Tundla Bypass to Ease Traffic

NHAI Plans Rs 794-Crore Etmadpur-Tundla Bypass to Ease Traffic
NHAI plans Rs 794-cr Etmadpur-Tundla bypass to ease traffic: Check route, cost, timeline - Roadways News · financialexpress.com

A new road is being planned to help traffic avoid Etmadpur and Tundla towns.

The road will be 16.2 kilometres long.

It will start near Kuberpur village and end near Garhijafar village in Uttar Pradesh.

The road will be built along National Highway 19.

It may have four or six lanes, plus service roads on both sides.

The project is expected to cost Rs 794.31 crore before GST.

Companies can submit their bids until November 5, 2026.

If the project proceeds, construction should take about two and a half years.

The completed road will then have five years of planned maintenance.

Key facts

Project
Etmadpur-Tundla greenfield bypass
Length
16.2 km
Estimated cost
Rs 794.31 crore, excluding GST
Route
Kuberpur village to near Garhijafar village on National Highway 19
Road design
Four- or six-lane divided carriageway with paved shoulders and two-lane service roads
Construction period
2.5 years
Maintenance period
Five years
Contract model
Engineering, Procurement and Construction contract