Sabarmati Bridge Completion Marks Bullet Train Project Milestone

Sabarmati Bridge Completion Marks Bullet Train Project Milestone
12-storey-high, 480m long: Sabarmati bridge takes Bullet Train project closer to completion · financialexpress.com

A new bridge for the Mumbai-Ahmedabad Bullet Train has been completed over the Sabarmati River in Ahmedabad.

It is 480 metres long and about 36 metres tall.

The height helps the rail route clear nearby roads, bridges, metro corridors and railway lines.

The bridge stands on eight large piers.

Its longer spans mean fewer piers are needed in the riverbed.

Workers built it in sections from the piers, joining the sections to form the bridge deck.

This method did not need temporary supports beneath the deck.

The bridge is one of 21 planned river bridges in Gujarat, and 18 are now complete.

Key facts

Bridge length
480 metres
Bridge height
Approximately 36 metres, or about 12 storeys
Location
Over the Sabarmati River in Ahmedabad
Nearby stations
About 1 km from Sabarmati station and 4 km from Ahmedabad station
Bridge piers
Eight circular piers, 6 to 6.5 metres in diameter
Gujarat bridge progress
18 of 21 planned river bridges completed
Total corridor river bridges
25: 21 in Gujarat and four in Maharashtra
Construction method
Balanced Cantilever Method

Quotes

National High Speed Rail Corporation Limited (NHSRCL)

The organization responsible for the Mumbai–Ahmedabad High-Speed Rail project.

“The construction of these segments required precision engineering, skilled manpower and quality check at every stage.”