1 hr ago
Revanth Reddy to Open Hyderabad Steel Flyover Thursday
A new flyover is opening in Hyderabad on Thursday.
It is called the Chanchalguda–Santoshnagar Steel Flyover.
The road is 3.32 kilometres long and has four lanes.
It connects several busy areas, including Chanchalguda, Saidabad and IS Sadan.
Today, a trip between Chanchalguda Printing Press and IS Sadan can take about 30 minutes in heavy traffic.
Officials expect the flyover to reduce that trip to about five minutes.
The project cost is reported as Rs.
620 crore, although the listed civil-work and land-acquisition figures add up to more.
The project was delayed for four years because of the Covid-19 pandemic and land acquisition problems.
It may also help people travelling to defence research offices.
Chief Minister A. Revanth Reddy will inaugurate the 3.32-km, four-lane Chanchalguda–Santoshnagar Steel Flyover on Thursday.
The corridor connects Chanchalguda, Saidabad and IS Sadan, enabling signal-free travel from Nalgonda crossroads to Owaisi Hospital.
The project includes a 2.53-km main viaduct and a 200-metre up-ramp at the IS Sadan junction.
The flyover is expected to cut peak-hour travel between Chanchalguda Printing Press and IS Sadan from about 30 minutes to five minutes.
The inauguration follows a four-year delay attributed to the Covid-19 pandemic and land acquisition issues.
- Who
- Chief Minister A. Revanth Reddy will inaugurate the flyover; Greater Hyderabad Municipal Corporation Commissioner R.V. Karnan inspected it.
- What
- The 3.32-km, four-lane Chanchalguda–Santoshnagar Steel Flyover will open to traffic.
- Where
- Hyderabad, connecting Chanchalguda, Saidabad and IS Sadan, from near Chanchalguda Printing Press toward Santoshnagar.
- When
- Thursday; the article does not provide a calendar date.
- Why
- To reduce congestion and travel times on the route and improve access to nearby defence establishments.
Key facts
- Length
- 3.32 kilometres
- Configuration
- Four lanes
- Reported project cost
- Rs. 620 crore
- Main viaduct
- 2.53 kilometres
- IS Sadan up-ramp
- 200 metres
- Expected travel-time reduction
- From around 30 minutes to around five minutes during peak hours
- Delay
- Four years, attributed to the Covid-19 pandemic and land acquisition issues
- Passenger Unit Count
- 70,576 in 2015 and 1,93,632 projected for 2035; the article does not specify the unit beyond PUC
Quotes
Md. Naveed
A commuter from Akbarbagh discussing the flyover’s expected effect on traffic.
“Finally, this flyover is being opened; while the works were underway, the traffic snarls were worse. Due to this flyover to reach Chandrayangutta from Malakpet, we can skip the Chanchalguda, Saidabad, Madannapet and IS Sadan, junctions that experience traffic jams.”
deccanchronicle.com