Khavda IV-C Transmission Corridor Supports India’s Green Transition
India is building more renewable-energy projects, such as solar and wind facilities.
Much of this energy is produced far from the cities and industries that use it.
Transmission lines work like large electricity highways that carry power over long distances.
The Khavda IV-C project is designed to move renewable electricity from Gujarat to Maharashtra.
Its Maharashtra section will cover about 306 circuit kilometres and pass through 150 villages.
The project is expected to improve power reliability in several parts of Maharashtra.
It will also connect with existing transmission lines serving Nashik and other areas.
Supporters say the project could help businesses, create jobs and encourage cleaner economic growth.
India is targeting 500 GW of non-fossil fuel capacity by 2030, with more than 300.5 GW reported as achieved by July 2026.
The Khavda region in Gujarat is emerging as a major renewable-energy generation hub.
The Maharashtra section of Khavda IV-C spans about 306 circuit kilometres across 150 villages and five talukas.
Four transmission lines are intended to move renewable electricity from Gujarat toward Maharashtra and strengthen regional power supplies.
The project is expected to support power reliability in Bhiwandi, Shahapur, Wada, Vikramgad and Nashik while easing pressure on existing networks.
- Who
- Resonia is developing the Khavda IV-C transmission project, which is intended to carry renewable power from Gujarat to Maharashtra.
- What
- A high-capacity transmission corridor involving four lines and approximately 306 circuit kilometres in Maharashtra.
- Where
- The project connects the Khavda region of Gujarat with Maharashtra, including areas around Bhiwandi, Shahapur, Wada, Vikramgad and Nashik.
- When
- The article was dated September 22 and cites India’s 2030 clean-energy target and capacity figures as of July 2026.
- Why
- To transport renewable electricity to areas that need it, strengthen grid reliability and support economic growth.
Key facts
- 2030 target
- 500 GW of non-fossil fuel capacity
- Reported capacity
- More than 300.5 GW as of July 2026
- Maharashtra project length
- Approximately 306 circuit kilometres
- Villages covered
- 150 villages across five talukas
- Transmission lines
- Four lines form part of the Maharashtra network
- Key regional connections
- The project will feed into the Nashik–Babhaleshwar line and connect with the Babhaleshwar–Padghe line at Boisar-II
- Expected beneficiaries
- Bhiwandi, Shahapur, Wada, Vikramgad and Nashik regions
Quotes
Ninad Pitale
Senior Vice President and Group Head of Corporate Affairs at Resonia
“India’s renewable-energy transition can achieve its full potential only when generation is matched by strong transmission infrastructure. Khavda IV-C is designed to create that critical link, moving renewable power from Gujarat to Maharashtra and supporting the state’s growing energy needs.”