SLBC Tunnel Clears Difficult Geological Stretch as Excavation Advances

SLBC Tunnel Clears Difficult Geological Stretch as Excavation Advances
SLBC Tunnel Gets Past Geological Challenge · deccanchronicle.com

Workers building the SLBC tunnel have passed through a very difficult section of rock.

They dug 700 metres over the last five to six months, working from both ends.

The tunnel is nearly 44 kilometres long and is about 79 per cent finished.

Some areas were unstable, so workers slowed down to improve safety.

The irrigation minister asked officials and the contractor to keep work moving while protecting the crews.

Concrete lining is already being added to finished parts.

The project is intended to bring water from the Srisailam reservoir to drought-prone areas.

Officials are working toward delivering water by June 2028.

Key facts

Excavation progress
700 metres over five to six months
Progress by tunnel end
About 450 metres from the outlet and 250 metres from the inlet
Main tunnel length
Nearly 44 kilometres
Main tunnel completion
About 79 per cent; around 9.1 kilometres remain
Water-delivery target
June 2028
Designed water volume
More than 30 tmc ft from the Srisailam reservoir
Tunnel 2 length
7.1 kilometres; lining work has resumed