India Bars Renewable Energy Projects Within 1 km of Borders

India Bars Renewable Energy Projects Within 1 km of Borders
Centre bars renewable energy projects within 1km of borders citing security concerns - Telegraph India · telegraphindia.com

The government of India has made new safety rules for building solar and wind power projects near the country's borders.

New solar, wind and hybrid energy projects cannot be built within 1 kilometre of the border.

The land close to the borders is now called a 'sensitive area,' and projects within 50 kilometres need special permission from the Home Ministry.

Projects within 20 kilometres of one border also need a no-objection certificate from the Defence Ministry.

Companies cannot hire workers from neighbouring countries like Pakistan, Bangladesh and China without asking the central government first.

Every project must have its own police post to watch over the construction work.

Companies must also pay for security equipment such as anti-drone systems, which are operated by police.

Buildings near the border cannot be tall, and hotels must be at least 5 kilometres away from the border.

Companies that already received permission before the new rules were announced do not have to apply again.

The government says these rules keep the country safe while still allowing clean energy projects to be built.

Key facts

Issuing authority
Ministry of Home Affairs (Internal Security wing)
Prohibited zone
Within 1 km of LoC, LAC and International Border
Sensitive area
Within 50 km of borders; MHA security clearance required
Defence NOC zone
Within 20 km of International Border
Restricted foreign labour
Pakistan, Bangladesh, China — barred without central government approval
Height caps
3 m (1-8 km), 5 m (8-20 km), 15 m (20-50 km)
Accommodation rule
Hotels at least 5 km from border; cafeterias within plant premises
Exemptions
Projects with prior MHA clearance or MoD NOC need not reapply

Quotes

Ministry of Home Affairs

Indian government ministry overseeing internal security

“All solar, wind and hybrid energy projects within 50 km will require security clearance from the Ministry of Home Affairs. The 1 km area will be strictly restricted, and no project activity will be permitted in this area.”