NMDC Commissions ₹5,427-Crore Integrated Iron Ore Project in Chhattisgarh

NMDC Commissions ₹5,427-Crore Integrated Iron Ore Project in Chhattisgarh
NMDC commissions Rs 5,427 crore iron ore project in Chhattisgarh · thehansindia.com

NMDC has started a new plant in Chhattisgarh that makes iron ore pellets.

The plant can make 2 million tonnes of pellets each year.

It is part of a much larger ₹5,427-crore project.

The project connects iron ore mines at Bacheli with a steel plant at Nagarnar.

A 135-kilometre pipeline will carry processed ore instead of relying only on trucks.

The project also includes a new ore-processing plant.

Ore fines and slimes from the Bailadila mines will be turned into concentrate and then pellets.

NMDC says the project strengthens its work from mining through pellet production and supports its long-term goal of reaching 100 million tonnes of production capacity.

Key facts

Project cost
₹5,427 crore
Pellet plant capacity
2 million tonnes per annum
Slurry pipeline capacity
15 million tonnes per annum
Pipeline length
135 kilometres
Pipeline route
Through 61 villages in Bastar and Dantewada districts
Technology
Straight Grate Induration technology
Long-term production target
100 million tonnes

Quotes

Amitava Mukherjee

Chairman and Managing Director of NMDC Ltd.

“This has not been an easy project to execute. It involved the processing facilities, the actual slurry pipeline, and the pellet plant. But today is a red-letter day—a day we have been waiting for a long time. This is the day when our collective dream is coming true.”