Telangana Prepares for Power Crisis Amid Coal Shortage

Telangana Prepares for Power Crisis Amid Coal Shortage
Power crisis looms large in Telangana · thehansindia.com

Telangana may face a shortage of electricity in the coming days.

Some power plants are producing less electricity because they do not have enough coal.

The Yadadri plant can produce 4,000 megawatts, but it is currently producing only 800 megawatts.

Officials said the plant has enough coal to continue at that level for only three or four days.

Low-quality coal has also caused problems in two units.

Telangana asked for five million tonnes of extra coal from Mahanadi Coal Limited.

The state says it has not received a response from Coal India or the Union Ministry of Power.

Chief Minister A Revanth Reddy has asked officials to estimate electricity needs for different sectors.

The government is preparing a plan to manage the possible crisis.

Key facts

Yadadri installed capacity
4,000 MW
Yadadri current generation
800 MW
Estimated remaining coal duration
Three or four days at the current generation level
Additional coal requested
Five million tonnes
Coal requested from
Mahanadi Coal Limited
Coal-stock standard cited
The Central Electricity Authority rules require at least 21 days of coal stocks for uninterrupted thermal generation
Additional concern
Officials said other projects could face similar problems if sufficient coal is not procured by September-end

Quotes

Telangana power officials

Officials discussing Telangana’s coal-supply and power-generation situation

“TG GENCO wrote a letter in August requesting the Coal India and also the Ministry of Power to allocate five million tonnes of additional coal from Mahanadi Coal Limited but there is no response from either Coal India or the union ministry till the date”