JSW Puts 50GWh India Battery Cell Plant On Hold
JSW Group wanted to build a very large factory in India to make battery cells.
The factory was planned to eventually produce 50GWh of cells.
JSW says it needs LFP technology, which is cheaper and stable for electric-vehicle batteries.
The company says this technology is difficult to obtain because China restricts technology transfers.
Because JSW has not found a technology partner, it has paused the factory project.
JSW can still assemble battery packs using cells imported from other countries.
Its battery-pack facilities for energy storage and MG vehicles are already operating.
The company says it continues to look for a way to make cells in India.
JSW Group has paused plans for a 50GWh battery cell gigafactory in India after failing to secure LFP technology.
Director Parth Jindal said China’s restrictions on technology transfers have made LFP technology difficult to obtain.
The original plan envisioned 10GWh by 2027 and 50GWh by 2032, built in three phases.
JSW’s battery-pack assembly facilities for JSW Energy’s storage business and MG Motor India have already been commissioned.
JSW says it still wants to make cells in India and continues searching for a technology partner.
- Who
- JSW Group, including director Parth Jindal and chairman and managing director Sajjan Jindal.
- What
- JSW has put its planned 50GWh Indian battery cell gigafactory on hold after failing to secure LFP technology.
- Where
- The proposed plant was planned near Nagpur, India.
- When
- The decision was disclosed on Wednesday; the previous plan targeted 10GWh by 2027 and 50GWh by 2032.
- Why
- JSW said it has not secured a technology tie-up for LFP cells and that access to the technology is restricted by China.
Key facts
- Planned capacity
- 50GWh of battery cell manufacturing
- Technology sought
- Lithium iron phosphate, or LFP
- Planned location
- Near Nagpur, India
- Original timeline
- 10GWh by 2027 and 50GWh by 2032, in three phases
- Current status
- The battery cell project is on hold
- Operational facilities
- JSW Energy’s battery-storage cell-to-pack line and JSW’s MG facility have been commissioned
- India’s cited cell production
- Ola Cell Technologies was identified as the only Indian company to have commissioned a cell plant, with an initial capacity of 1.4GWh
- Import dependence
- India’s lithium-ion cell imports rose 64% year-on-year to Rs 41,667 crore in FY26, with China accounting for 84%
Quotes
Vikramadithya Gourineni
Executive Director of Amara Raja Energy & Mobility
“There is a bit of policy uncertainty. There have been export controls and restrictions on technology access. Our own tech partnership has not gone ahead. It’s become an in-house effort. There have been some stumbling blocks.”
businesstoday.in
“We have not yet secured a technology tie-up, and hence that project currently is on hold. LFP is not available anywhere in the world outside of China, and right now they are guarding it like a weapon.”
livemint.com