Orissa High Court Slams Cuttack’s Endless Pothole Cycle

Orissa High Court Slams Cuttack’s Endless Pothole Cycle
Orissa High Court cites Kafka, Shakespeare to slam Cuttack’s endless pothole nightmare · indianexpress.com

The Orissa High Court is worried about the poor condition of roads in Cuttack.

Many roads develop potholes after repairs and the rainy season.

The court has been monitoring the problem since 2020.

It said official reports and promises have not led to roads that people can safely use.

Government officials promised to prepare a larger plan for road repairs and preventing waterlogging.

They also said that 64 out of 105 road and drain projects were finished.

The court questioned a claim that 70% of major roads were in good condition.

Local legal groups will now inspect roads and report what they find.

Key facts

Case type
Suo motu public interest litigation concerning Cuttack’s roads and waterlogging.
Monitoring period
The matter has been before the court since 2020.
Completed works
Authorities reported that 64 of 105 road and drain works had been completed.
Earlier repair directive
Authorities were directed to repair damaged roads in 15 wards on September 12, 2024.
Arterial-road claim
The Cuttack Municipal Corporation said 70% of arterial roads were in good condition.
New reporting deadline
Ward-level advocates’ committees were directed to submit comprehensive road reports within seven days.
Next hearing
September 10.

Quotes

Orissa High Court, represented by Justices K R Mohapatra and V Narasingh

The High Court bench hearing the suo motu PIL concerning Cuttack’s roads and waterlogging

“Compliance affidavit(s) have not translated themselves to motorable roads, and the scenario remains the same with an agonising cycle: potholes-repairs-onset of monsoon and again potholes. It is akin to Shakespeare’s ‘grief’ with a thousand Shrieks (King Lear, Act 2).”