NCLAT Seeks Project-Wise Timelines for 16 Supertech Projects

NCLAT Seeks Project-Wise Timelines for 16 Supertech Projects
NCLAT seeks project-wise completion timelines for 16 stalled Supertech projects taken up by NBCC · CNBC TV 18

Sixteen unfinished housing projects built by Supertech are being taken over by NBCC.

A committee appointed to oversee the work gave a broad estimate that projects may take 12 to 36 months to complete.

It did not give a separate finish date for each project.

A tribunal called NCLAT has asked the committee to provide those dates and say how much money is available.

The committee must file this information before the next hearing on November 6, 2026.

Work preparations include checking the projects, getting approvals and selecting contractors.

Some expected sources of funding may not be available until around March 2027.

Contractors could temporarily pay for some work themselves and receive interest if project funds are short.

Key facts

Projects
16 stalled Supertech housing projects taken up by NBCC
Broad completion estimate
12 to 36 months
Next hearing
November 6, 2026
Due diligence and audit
Proposed to be completed by January 15, 2027
Expected tender packages
27 or more separate packages through open e-tendering
Potential contractor financing
Contractors may self-finance work for an initial six months and receive 6–7% annual interest on deferred amounts
Insolvency proceedings
Initiated over a Union Bank of India plea filed on March 20, 2021

Quotes

NCLAT bench

Three-member insolvency appellate tribunal bench comprising Justice Yogesh Khanna, Barun Mitra and Ajai Das Mehrotra.

“We request the Apex Court Committee to file a report of tentative completion date in each of the 16 projects, as each project is at a different stage of construction and such report/affidavit may also disclose the finances available as of today and it be filed prior to the next date of hearing and the matter be listed for further orders on 06.11.2026.”
CNBC TV 18