Green Energy Corridor Advances India’s 2035 Clean Power Goal

Green Energy Corridor Advances India’s 2035 Clean Power Goal
Green energy scheme ‘big push’ towards achieving 900 GW non-fossil capacity by 2035: PM Modi · thehansindia.com

India’s government approved a plan to build stronger electricity networks.

The plan will help move up to 135 GW of renewable electricity between states and Union Territories.

It will also add 50 GWh of battery storage.

Batteries can save electricity and provide it when solar and other renewable sources are not producing enough.

Prime Minister Narendra Modi said the plan will help India reach 900 GW of non-fossil power capacity by 2035.

The project is expected to be completed by FY 2032-33.

It is intended to create jobs in construction, manufacturing, energy storage, and grid management.

India already had 300.50 GW of non-fossil capacity by July 31, 2026.

Key facts

Renewable-energy evacuation
Up to 135 GW
Battery storage
50 GWh of Battery Energy Storage Systems
Implementation target
FY 2032-33
Reported project outlay
Rs 1,86,405 crore
Central financial support
Rs 54,082 crore
Non-fossil capacity
300.50 GW as of July 31, 2026
Total installed power capacity
552 GW as of July 2026
Outlay detail
The article lists Rs 1,36,378 crore for intra-state transmission and Rs 50,000 crore for storage, which totals Rs 1,86,378 crore, differing from the reported total outlay.

Quotes

Narendra Modi

Prime Minister of India

“The Cabinet decision on the Green Energy Corridor Phase III will ensure: 135 GW renewable energy evacuation. 50 GWh battery storage. Stronger power grids across States and UTs. More jobs in manufacturing, construction, and energy storage. Big push towards 900 GW non-fossil capacity by 2035,”
thehansindia.com