Mogra Pumping Station Work Begins After Two-Decade Wait

Mogra Pumping Station Work Begins After Two-Decade Wait
Mogra Pumping Station Work To Begin On October 15 After 20-Year Wait, To Ease Andheri Flooding · freepressjournal.in

Mumbai often gets flooded during heavy rains.

The city plans to build a new pumping station near Mogra nullah.

Work is scheduled to start on October 15, after the project received environmental clearances.

The station will help move rainwater toward the sea, including when high tides make drainage harder.

It is expected to help areas such as Versova, Andheri and Jogeshwari.

The project was delayed by land issues and a road project, and its location had to be changed.

It is part of a much larger plan to improve Mumbai’s flood protection.

The civic body hopes the station will be working before 2029.

Key facts

Project cost
₹393 crore
Scheduled start
October 15
Original sanction
2021
Original deadline
24 months
Current target
Commissioning before 2029
Wider flood-control plan
Mumbai’s ₹13,000-crore Integrated Flood Control Action Plan
Key delay factors
Land acquisition hurdles and a site conflict with Phase 2 of the Versova–Dahisar Coastal Road

Quotes

Senior civic official

Civic official discussing Mumbai’s flood-control plan.

“The Mogra Pumping Station is a key component of the plan.”
freepressjournal.in

Dhaval Shah

Co-founder of the Lokhandwala Oshiwara Citizens Association.

“The project is already delayed and should now be completed on priority to ease flooding in Link Road, Veera Desai Road and other low-lying areas in Andheri. Sofas and other bulky waste are being thrown into nullahs, choking the waterway and reducing its capacity. The civic body must also crack down on dumping in the nullah.”
freepressjournal.in