BMC to End Powai Lake Sewage Inflow, Build STP

BMC to End Powai Lake Sewage Inflow, Build STP
Mumbai: Powai Lake Sewage Inflow To Stop From October 1; BMC Targets STP By May 2027 · freepressjournal.in

Powai Lake has been receiving a lot of sewage from nearby areas.

The BMC says this sewage will stop entering the lake from October 1, 2026.

Workers have connected 20 sewage outlets to treatment plants instead.

A new treatment plant is expected to start working by May 2027.

It will clean 8 million litres of sewage each day.

Another 8 million litres will be sent to the Bhandup treatment plant.

Sewage helped water hyacinth, a fast-growing aquatic plant, spread across the lake.

The BMC has already removed most of the estimated water hyacinth and plans to study more ways to improve the lake’s water quality.

Key facts

Sewage inflow
About 18 million litres entered Powai Lake daily before diversion work.
Intercepted outflows
20 sewage outflows have been intercepted.
New sewer lines
3,056 metres of sewer lines were laid.
Planned STP capacity
The Powai plant will treat 8 million litres of sewage daily.
Water hyacinth removed
20,340 metric tonnes, or 85% of the estimated quantity, had been removed by September 29, 2026.
Lake size
Powai Lake has a water spread of 223 hectares and a catchment area of about 600 hectares.
Lake construction
Powai Lake was built in 1891.