More Vande Bharat Sleeper Trains Delayed Until March 2027

More Vande Bharat Sleeper Trains Delayed Until March 2027
When will India get more Vande Bharat Sleeper trains? Here’s the latest timeline · financialexpress.com

India is planning more Vande Bharat trains for overnight journeys.

These trains are called Vande Bharat Sleeper trains because they will have sleeping coaches.

The first new train prototype is being built in Latur, Maharashtra.

It is now expected sometime before March 31, 2027.

Earlier, the target was June 2026, so the schedule has moved later.

Rail Vikas Nigam Limited is working with a Russian company called Transmashholding.

Their joint venture plans to make 120 trainsets with 16 coaches each.

The companies have not yet said when passengers can start using these trains.

Key facts

First prototype timeline
Expected during the financial year ending March 31, 2027.
Earlier target
June 2026, according to PTI.
Planned production
120 Vande Bharat Sleeper trainsets.
Coaches per trainset
16 coaches.
Manufacturing location
Upgraded Marathwada Rail Coach Factory in Latur, Maharashtra.
Joint venture
Kinet Railway Solutions Ltd., formed by RVNL and Transmashholding.
Passenger service date
Not provided by RVNL.

Quotes

Saleem Ahmed

RVNL Chairman and Managing Director

“Over the years, RVNL has built strong capabilities in complex rail infrastructure with a presence across 16 states and an expanding international footprint.”
financialexpress.com