2 hrs ago
NGT Orders Fresh Kerwa Dam Full Tank Level Survey
The National Green Tribunal has told officials to restart a survey around Kerwa Dam in Bhopal.
The survey will check the dam's Full Tank Level boundary.
Officials will use satellite pictures, drone images, maps and visits to the site.
They will also check government records and physically verify the land.
An earlier report listed 33 constructions inside the area being examined.
Eighteen were recorded on government land and 15 on private land.
Some submitted records linked properties to public figures and their relatives.
Officials must check whether the old boundary markers are still present and correctly placed.
The committee has three weeks to give the tribunal a final report.
The National Green Tribunal ordered the resumption of the Kerwa Dam Full Tank Level survey in Bhopal.
The survey must include satellite and drone imagery, ground-truthing, physical verification, government records and topographical maps.
A previous report identified 33 constructions in the FTL area: 18 on government land and 15 on private land.
The committee must verify the listed properties, remaining boundary pillars and whether the demarcation matches official records.
The committee has three weeks to submit its final report, with the next hearing scheduled for October 29.
- Who
- The National Green Tribunal's Central Zone Bench, a survey committee and petitioner Rashid Noor Khan.
- What
- The tribunal ordered the resumption and fresh verification of the Kerwa Dam Full Tank Level survey.
- Where
- Kerwa Dam in Bhopal, Madhya Pradesh.
- When
- The hearing took place on Wednesday, the order was issued on Thursday, and the next hearing is scheduled for October 29.
- Why
- To verify the current FTL demarcation, boundary pillars and 33 constructions identified in an earlier report.
Key facts
- Survey deadline
- Three weeks to complete the exercise and submit a final report.
- Earlier constructions identified
- 33 total: 18 on government land and 15 on private land.
- Reported submerged area
- Approximately 462.150 hectares.
- Earlier demarcation
- The boundary was marked using 1,080 concrete blocks and pillars.
- Required evidence
- Satellite imagery, drone surveys, ground-truthing, government records and topographical maps.
- Additional assessment
- The dam's height and the buffer zone will be considered in determining the FTL.
- Next hearing
- October 29.