1 week ago

Juhu redevelopment gets relief as defence height restrictions ease

Juhu redevelopment gets relief as defence height restrictions ease
One of the most premium Mumbai neighbourhoods is set for a massive overhaul · CNBC TV 18

A rule had stopped many buildings in Juhu from becoming taller than a few floors.

This made it difficult for old housing societies to rebuild their homes.

Many families moved out for redevelopment but were left waiting when projects stopped.

On August 3, 2026, the Ministry of Defence reduced the restricted area around a defence station from 500 metres to 100 metres.

This means nearly 200 societies can now explore redevelopment more easily.

New buildings might be eight to 10 floors tall, but each project still needs approval related to Mumbai airport flight paths.

Some builders have already shown interest.

Residents still need new permissions, and people inside the remaining 100-metre zone have not received the same relief.

Key facts

Affected societies
Around 200 residential societies in Juhu were affected by the former 500-metre restriction zone.
Former restriction
SRO 150 limited construction within 500 metres of the Juhu Signalling Transmission Station and capped building height at 15.24 metres.
New restriction
The restricted zone has been reduced to 100 metres.
Potential building height
Buildings may potentially reach 32–34 metres, or about eight to 10 storeys, subject to approvals.
Property prices
Juhu prices are currently approximately ₹80,000 to ₹1.2 lakh per square foot, compared with ₹40,000–50,000 in 2010–2011, according to Knight Frank figures cited in the article.
Rent pressures
Tara Apartments residents were promised ₹35,000 monthly rent in 2010–2011; current rents can exceed ₹80,000, while premium residences can cost ₹2.5 lakh to ₹5 lakh monthly.
Remaining approvals
Projects still require fresh NOCs and case-by-case Airports Authority of India approval linked to the airport flight funnel zone.

Quotes

A resident of Tara Apartments

Unnamed Tara Apartments resident affected by stalled redevelopment

“"It has been painful," said a resident of Tara Apartments, who did not wish to be named. "There were some dilapidated buildings in the radius and people were getting really stressed. Builder communication was case by case, and things only got more complicated with the ongoing and stuck projects. It took a long time, but finally there is some good news."”
CNBC TV 18

Amit Jagani

Member of the Juhu Wireless Affected Residents Association (JWARA)

“"Over the years, the society has incurred substantial expenditure on recurring repairs merely to keep the building habitable. The restrictions imposed under SRO 150 further compounded our difficulties, with even reputed builders and our own acquaintances reluctant to undertake the redevelopment project."”