Kanpur Metro Reaches 80% Completion as Ninth Train Arrives

Kanpur Metro Reaches 80% Completion as Ninth Train Arrives
Kanpur Metro gets 9th Corridor-2 train: How much of the Rs 11,076-crore project is complete? · financialexpress.com

Kanpur is building a metro system with two main routes.

The whole first phase will cover about 32.4 kilometres and have 29 stations.

Trains already carry passengers between IIT Kanpur and Kanpur Central.

Government figures say about 80% of the project’s construction is complete.

A second route will run from Chandra Shekhar Azad Agricultural University to Barra-8.

Nine of the 10 trains needed for that route have arrived in Kanpur.

Tunnelling for the second route has also been completed.

Workers still need to finish construction, safety checks and other systems before the route can open.

The project was approved at a cost of about ₹11,076 crore.

Key facts

Total Phase-I length
32.385 kilometres
Physical progress
80.45% as of February 28, 2026
Financial progress
78.5% as of February 28, 2026
Operational section
IIT Kanpur to Kanpur Central, reported as 15.1 to approximately 16 kilometres
Operational stations
14 stations
Original sanctioned cost
₹11,076.48 crore
Corridor-2 trains received
9 of 10
Corridor-2 route
Chandra Shekhar Azad Agricultural University to Barra-8, 8.6 kilometres