Mumbai Airport Plans Terminal 1 Revamp, Shifting Flights to Navi Mumbai

Mumbai Airport Plans Terminal 1 Revamp, Shifting Flights to Navi Mumbai
Mumbai airport T1 redevelopment - how passengers will be affected as 265 international flights move to Navi Mumbai · livemint.com

Mumbai’s main airport is planning to rebuild part of its old Terminal 1.

To make room for the work, some flights are expected to move to Navi Mumbai airport and some Terminal 1 flights to Terminal 2.

MIAL says at least 265 weekly international flights will move to Navi Mumbai by October 25.

The first demolition phase is planned for the north section of Terminal 1B and is due to start on January 15, 2027.

The airport operator says the move to Navi Mumbai is temporary.

It estimates that about five million passengers could be affected.

People travelling to Navi Mumbai may need more time and money to get to the airport.

The operator expects most Mumbai airport passengers to be unaffected and says the changes should help limit disruption.

Key facts

Weekly international flights at issue
At least 265 of 770 are planned to move to Navi Mumbai International Airport.
Flight-shift deadline
October 25.
Terminal 1B demolition
The north section is planned for demolition beginning January 15, 2027.
Terminal 1 current capacity
Around 15 million passengers per annum (mppa).
Terminal 1 capacity after redevelopment
The Adani Group says capacity will rise by 33% to 20 mppa.
Passengers expected to be temporarily affected
Around five million, or nearly 9% of Mumbai airport’s annual passenger traffic, according to the Adani Group.
Passengers expected to remain unaffected
91%, according to Adani Airport Holdings Limited CEO Arun Bansal.

Quotes

Vishnu Mohan Jha

Chief Airport Officer of MIAL

“91% of Mumbai Airport’s passenger traffic will remain unaffected even as we undertake redevelopment of the age-old infrastructure that was in urgent need of repairs. Only the North Section of Terminal 1B, which accounts for around one-third of T1 of Mumbai Airport’s capacity, is being demolished in Phase 1 to minimise passenger inconvenience and operational disruption. The transition to Navi Mumbai Airport is temporary and does not represent a permanent shift of Mumbai Airport traffic.”