Finland Halts Work at Google Data Centre Sites

Finland Halts Work at Google Data Centre Sites
Google's $15 billion AI bet hits a green hurdle: Why Finland has halted work at two data centre sites? · livemint.com

Google wants to build more places in Finland that hold computers used for artificial intelligence.

Before building, companies may need to study how their plans could affect nature.

Finnish authorities say work such as cutting trees and changing land may have happened before the required studies were completed.

They have ordered work to stop at two planned sites while they look into the matter.

Google says it understands the concerns and will follow the authorities’ guidance.

The company also says it plans to plant trees at one site.

Finland’s environment minister said the issue could delay the projects.

The order does not cancel Google’s wider investment in Finland.

Key facts

Company investment
Google announced a €13 billion investment, about $15 billion, in Finnish digital infrastructure over two years.
Sites affected
Planned data centre sites in Muhos and Kajaani.
Agency
Finnish Supervisory Agency (LVV).
Response deadline
Tuike Finland was asked to explain the work and its plans by 14 October.
Work suspension deadline
Preparatory work was to stop by 23 October.
Muhos tree planting
Google said its biodiversity plans include tree planting across 130 hectares at Muhos.
Reported clearance
The Finnish Association for Nature Conservation’s chair said more than 300 hectares had been deforested in the area.

Quotes

Hanna Halmeenpaa

Chair of the Finnish Association for Nature Conservation

“We understand the concerns and have fallen short of our own high standards in this instance.”
livemint.com
“We will study the LVV's findings and follow their guidance.”
livemint.com