NFR Official Reviews Progress of Jiribam-Imphal Railway Project

NFR Official Reviews Progress of Jiribam-Imphal Railway Project
Top NFR official reviews progress of Jiribam-Imphal railway project · theprint.in

A railway line is being built to connect Jiribam with Imphal in Manipur.

A senior railway official visited parts of the unfinished project to check its progress.

The railway must pass through difficult hills and mountains.

Workers are building many tunnels and bridges along the route.

The project has 54 tunnels and 131 bridges in total.

One bridge at Noney will have very tall supporting pillars.

Officials are also preparing for a safety inspection planned for October.

The railway authorities want the remaining work completed safely and on time.

Some sections of the line are already operating, while other sections are still under construction.

Key facts

Project length
110.625 km
Tunnel network
54 tunnels totaling approximately 66.47 km
Bridges
15 major bridges and 116 minor bridges
Tallest bridge
Bridge No. 164 at Noney, with pier height of 141 metres
Stations
11 railway stations are planned on the line
Commissioned sections
Jiribam-Vangaichungpao in February 2017; Vangaichungpao-Khongsang in September 2022
Upcoming review
Commission of Railway Safety inspection planned for October