House panel flags Eklavya school construction delays, seeks solutions
The Indian government wanted to build special schools called Eklavya Model Residential Schools for tribal children.
In these schools, children from tribal communities can live and study with modern classrooms and labs.
A group of people called a parliamentary committee checks whether the government is doing its work well.
The committee looked at how these schools are being built and found the work is going very slowly.
Of 728 approved schools, only 428 have been finished.
Building is still happening at 249 places, and 51 schools have not even started construction.
Many schools, 118 of them, are still running from government or rented buildings instead of their own permanent buildings.
Because building is slow, the cost of construction is going up, so the schools need more money.
The committee asked the government to find a new and better way to speed up the work.
It also suggested setting up a separate agency to keep a close watch on the building progress.
The Standing Committee on Social Justice and Empowerment flagged repeated delays in constructing Eklavya Model Residential Schools for tribal students.
Only 428 of 728 sanctioned EMRS have been completed, with construction underway at 249 locations and 51 schools at the pre-construction stage.
The panel said 118 schools still function from government or rented buildings, lacking infrastructure like technology and AI labs and smart classrooms.
It warned that delays are escalating construction costs, requiring a higher budget allocation for the National Education Society for Tribal Students.
The committee urged the Ministry of Tribal Affairs to develop an 'alternative solution' and suggested setting up an independent agency to monitor progress.
- Who
- The parliamentary Standing Committee on Social Justice and Empowerment, the Ministry of Tribal Affairs, and the National Education Society for Tribal Students.
- What
- The committee flagged delays in the construction and operationalisation of Eklavya Model Residential Schools for Scheduled Tribe students, along with rising costs.
- Where
- India
- When
- The report was tabled in both Houses of Parliament on Monday; construction data is as of April 30, 2026.
- Why
- To speed up completion of residential schools for tribal students and address cost escalation caused by construction delays.
Key facts
- Scheme
- Eklavya Model Residential Schools (EMRS)
- Target schools
- 728
- Completed schools (April-end)
- 428
- Schools under construction
- 249
- Schools at pre-construction stage
- 51
- Schools in government/rented buildings
- 118
- Budget estimate 2026-27
- Rs 7,150.01 crore
- Managing body
- National Education Society for Tribal Students
Quotes
Standing Committee on Social Justice and Empowerment
Parliamentary committee on social justice and empowerment
“The committee feels that some alternative is to be developed by the ministry as these problems are recurring. The measures taken have not been able to resolve the issues.”