Commissioner Urges Faster 100-Foot Master Plan Road Widening

Commissioner Urges Faster 100-Foot Master Plan Road Widening
Commissioner calls for expediting proposed Master Plan Road from Gopalapatnam junction · thehansindia.com

Visakhapatnam officials want to make a planned road much wider.

The road would run from Gopalapatnam Junction Arch to Old Goshala.

It is planned to be 100 feet wide and 3.10 kilometres long.

The commissioner wants the work finished in 120 days.

Officials say 348 properties may be affected by the widening.

They will first survey the road and mark where it will go.

Some buildings and a part of a temple may need changes.

The government says affected people will receive compensation according to the rules.

Key facts

Road stretch
3.10 km from Gopalapatnam Junction Arch to Old Goshala
Planned width
100 feet
Completion target
120 days
Affected properties
348 total: 210 on the right side and 138 on the left side
Compensation
GVMC said it would provide appropriate structural compensation according to norms
Project responsibilities
GVMC will ensure the Right of Way and execute construction; VMRDA will provide funding for required infrastructure
Planned infrastructure
Centre medians or dividers, retaining or protection walls, and other necessary works