2 hrs ago
Tata Power Commissions 400 kV Jalpura-Khurja Transmission Corridor
Tata Power has completed a new electricity transmission project in Uttar Pradesh.
The project connects Khurja and Jalpura.
It includes two transmission circuits covering 162 circuit kilometres.
A special substation was also built at Jalpura.
The substation can handle 1,000 MVA of electricity transformation capacity.
Khurja is an important power connection point in western Uttar Pradesh.
The corridor is intended to help move electricity toward the National Capital Region and Noida.
Tata Power says its transmission network now covers 7,900 circuit kilometres that are operating or being built.
Tata Power commissioned the 400 kV Jalpura-Khurja transmission corridor in Uttar Pradesh.
The project includes a double-circuit transmission line spanning 162 circuit kilometres.
It also features a gas-insulated switchgear substation at Jalpura.
The substation has a transformation capacity of 1,000 MVA.
Tata Power’s transmission portfolio now totals 7,900 circuit kilometres operational and under execution across India.
- Who
- Tata Power commissioned the transmission corridor.
- What
- A 400 kV Jalpura-Khurja corridor comprising a 162-circuit-kilometre double-circuit line and a 1,000 MVA substation.
- Where
- Between Khurja and Jalpura in Uttar Pradesh, India.
- When
- Thursday, with the announcement published on September 3, 2026.
- Why
- To support efficient power transmission toward the National Capital Region and Noida.
Key facts
- Project
- 400 kV Jalpura-Khurja transmission corridor
- Location
- Uttar Pradesh, India
- Transmission line
- Double-circuit line spanning 162 circuit kilometres
- Substation
- Gas-insulated switchgear substation at Jalpura
- Transformation capacity
- 1,000 MVA
- Transmission portfolio
- 7,900 circuit kilometres operational and under execution across India
- Announcement date
- September 3, 2026