Fund Diversion Dispute Erupts at Bhopal Council Meeting

Fund Diversion Dispute Erupts at Bhopal Council Meeting
Fund Diversion Row Rocks Bhopal Municipal Corporation Council Meeting · freepressjournal.in

A city housing project in Bhopal has caused an argument among council members.

The argument is about money meant for homes for economically weaker families.

The money was originally linked to a project at 12 Number Stop.

Some of it was used for a delayed housing project in Baghmugalia.

The Baghmugalia project began in 2019 but was not finished by its planned deadline.

Its first contractor was removed after failing to complete the work.

The city says the money was shifted because people waiting for Baghmugalia homes staged repeated protests.

The opposition wants clearer information about the transfer and project spending.

A municipal committee member said officials had not given her enough details.

Key facts

Baghmugalia project launch
2019
Planned housing units
768: 336 EWS, 288 LIG and 144 MIG units
Original completion deadline
2022
Original contractor
M/s Gulshan Rai Jain (Second); work order issued February 4, 2019
Contract termination
August 29, 2024, after repeated extensions and non-completion
Replacement contractor
M/s Pelji Ratna Sorathia Infra Pvt Ltd; work order issued September 19, 2024
Units completed by replacement contractor
432 unfinished units, according to the article
Fund adjustment
Funds for two surrendered EWS blocks under Project No. 12 were added to the Baghmugalia project balance

Quotes

Chhaya Thakur

Mayor-in-Council member of Bhopal Municipal Corporation

“Corporation officials do not listen to me, I have been frustrated for four years.”
freepressjournal.in