2 weeks ago

CERC lets renewable developers pay to keep grid connections

CERC lets renewable developers pay to keep grid connections
CERC tariff order: Renewable developers get nearly 12-month grid extension for up to Rs 6,000/MW daily fee · financialexpress.com

In India, companies build big solar and wind farms that need permission to connect to the electricity grid.

Sometimes a company is late finishing its project, and before, it could lose that permission right away.

A special electricity court called CERC has made a new rule: a late company can pay a daily fee and keep its grid permission a little longer.

The fee gets bigger the longer the company is late, but it must first show it has bought some land and started working.

Different types of delay have different fees and time limits.

The money collected is used to lower electricity transmission charges for other power buyers.

If a company still does not finish in time, it loses its permission and its bank guarantee.

This rule gives almost-finished projects a fair chance to be completed.

Key facts

Regulator
Central Electricity Regulatory Commission (CERC)
Commissioning delay charge
Rs 3,000/MW/day, rising to Rs 6,000/MW/day in months 10-12
Land/financing extension charge
Rs 1,000/MW/day, rising to Rs 1,200-1,300
Maximum extensions
3 months (land), 6 months (financing), 12 months (commissioning)
Capacity facing revocation
At least 5.3 GW up to October (CTUIL data)
Eligibility – land
20% land for land/financing; 50-75% land for commissioning depending on route
Use of compensation
100% of CoD fees and 50% of land/financing fees cut Monthly Transmission Charges under Sharing Regulations 2020
Stakeholder comments
42 stakeholders, including developers, discoms, CTUIL and industry bodies

Quotes

Srivatsan Iyer

Global CEO, Hero Future Energies

“It is noted that such entities have been holding on to the connectivity, a scarce resource; therefore, additional time should be allowed, with payment of compensation, irrespective of the reasons for such delay, in a graded manner to ensure the earliest compliance with the milestones”
financialexpress.com indianexpress.com
“The entities seeking such time are at various stages of implementation of the project, including some at an advanced stage of implementation. Several such cases have been disposed of by this commission, giving additional time on payment of compensation”
indianexpress.com

Sources

Related news