Gaur Chowk Underpass Opening Delayed Again, Commuters Face Congestion

Gaur Chowk Underpass Opening Delayed Again, Commuters Face Congestion
“Stuck for an hour to cross 2 km”: Noida’s Gaur Chowk underpass delayed again, commuters wait for relief · indianexpress.com

Gaur Chowk is a very busy intersection in the Greater Noida area.

A new underpass is being built so vehicles can avoid some of the traffic.

It was supposed to open in mid-August, but officials now expect it to open in late October.

Workers have faced shortages of bitumen and other supply problems.

They also had to work carefully around electricity, gas and sewage lines.

Heavy traffic left little room and time for construction.

Many people now spend much longer than expected crossing the area.

Officials are repairing a rain-related problem and adding protection against water.

They say the underpass will be opened only after the remaining work and safety tests are finished.

Key facts

Project cost
Rs 82 crore
Underpass length
700 metres
Current completion
About 90 percent
Expected opening
Late October, close to Diwali
Daily traffic
About one lakh vehicles pass through Gaur Chowk
Main connection
Surajpur to Gaur City, parallel to the Taj Highway
Remaining work
Bitumen work, lighting, painting, water-protection measures and testing

Quotes

Jitendra Kumar

A 27-year-old app-based bike taxi driver who works across the National Capital Region.

“It will save me time, and I can take more rides.”
indianexpress.com
“So we see the traffic jam, and we refuse to go.”
indianexpress.com

Rhaees

A 28-year-old air-conditioner repair technician commuting from Ghaziabad to Surajpur.

“Some customers understand. But every time I can’t be late.”
indianexpress.com