Srisailam Hydroelectric Unit 4 Back on Grid After Six Years

Srisailam Hydroelectric Unit 4 Back on Grid After Six Years
Srisailam hydro-electric plant’s 4th unit resumes operations after 6 years · thehansindia.com

There is a big power station in India called Srisailam that makes electricity using the force of water.

Inside the station are six machines called units, and the one that broke can make 150 megawatts of electricity.

In August 2020, one of these machines, called Unit 4, caught fire and was very badly damaged.

Sadly, nine engineers lost their lives in the fire, and the machine could not make electricity anymore.

Two companies were hired to fix the machine, and they worked on it over many years.

The repairs were hard — the machine started working a couple of times but then stopped again because of new problems.

Engineers from India and Japan kept finding and fixing the problems, like loose parts inside the machine.

Finally, in August 2026, the machine was connected back to the electricity grid, so it can make power again.

Now all six machines are working, which means the station can help supply electricity to people, especially when they need it most.

Key facts

Station
Srisailam Left Bank Hydro Electric Station (SLBHES)
Total capacity
900 MW (6 x 150 MW)
Restored unit
Unit 4, 150 MW
Location
Eegalappenta, Nagarkurnool district, Telangana
Fire incident
August 20, 2020
Casualties and loss
Nine engineers killed; about Rs 180 crore estimated loss
Repair firms
Shree Abirami Engineering Works, Voith Hydro Pvt Ltd, HM Hydro (Japan)
Grid synchronization
August 11, 2026 (3:21 am per one report)

Quotes

Top officials of the TS Genco

Officials from Telangana State Genco power utility

“After obtaining permission for charging the Generator of Unit-4 from the government, the Genco carried out all necessary pre-commissioning tests and successfully synchronised it to grid on Tuesday evening.”
thehansindia.com
“Fine-tuning works such as dynamic balancing, turbine auto-tuning etc. have also been taken up for ensuring smooth running of the Unit 4”
thehansindia.com