Nava Limited Commissions 100 MW Solar Plant in Zambia

Nava Limited Commissions 100 MW Solar Plant in Zambia
Nava Limited Announces Commissioning of 100 MW Solar Project in Zambia; Begins Power Evacuation · theprint.in

Nava Limited has started operating a large solar power plant in Zambia.

The plant can produce 100 megawatts of electricity.

Electricity from the plant is now being sent to Zambia’s national grid.

A company called Maamba Solar Energy Limited operates the project.

It has agreed to sell all the electricity to Zambia’s national power utility for 20 years.

Nava says the project expands its business into renewable energy.

The company also wants to build more clean-energy projects in different countries.

The project is partly owned by Nava Global and partly by a Zambian investment company.

Key facts

Project capacity
100 MW
Project operator
Maamba Solar Energy Limited
Power purchaser
ZESCO Limited, Zambia’s national power utility
Power purchase agreement
20 years
Ownership
65% Nava Global and 35% ZCCM Investments Holdings PLC
Status
Commissioned; power evacuation has commenced
Parent company
Nava Limited

Quotes

Ashwin Devineni

Managing Director and CEO of Nava Limited

“This milestone reflects our commitment to sustainable growth and reinforces our vision of building a diversified, future-ready energy portfolio across geographies.”
theprint.in
“The commissioning of our 100MW solar project in Zambia marks a defining step in Nava’s journey into renewable energy.”
theprint.in