Bhopal Sets March 31 Deadline to Clear Aadampur Legacy Waste

Bhopal Sets March 31 Deadline to Clear Aadampur Legacy Waste
New Agreement To Clear Aadampur Legacy Waste; Bhopal Municipal Corporation Sets March 31 Deadline · freepressjournal.in

Aadampur, near Bhopal, has a very large pile of old garbage.

The city corporation has made a new agreement with a private agency to process it.

The agency is supposed to finish clearing the site by March 31.

About 4 lakh metric tonnes of old waste are still there.

The project is expected to cost Rs 55 crore.

The company has started work with three machines and about 55 workers.

Some material made from the waste is sent to cement plants.

Fires have happened at the site, and the city corporation says it will watch the work.

The city also spends money separately to manage new garbage arriving there.

Key facts

Legacy-waste site
45 acres
Waste targeted for removal
Around 6.5 lakh metric tonnes
Waste remaining
Around 4 lakh metric tonnes, according to the BMC
Cleanup project estimate
Rs 55 crore
Processing equipment
Three machines: two rated at 250 tonnes per hour each and one at 300 tonnes per hour
Staff deployed
Around 55 workers
Fresh-waste management
Around Rs 21 crore, separate from legacy-waste clearance