Sewri-Worli connector delayed to early 2027

Sewri-Worli connector delayed to early 2027
Deadline pushed by 4 months: Sewri Worli connector to miss September deadline, to be opened early 2027 · indianexpress.com

The Sewri-Worli connector and the reconstructed Elphinstone bridge in Mumbai are going to be delayed.

The new deadline is early 2027 instead of September 2026.

The delay is because of many things like taking longer to dismantle the old bridge, unexpected work, complaints from residents, not enough workers, and the rainy season.

The bridge is 132 meters long and needs 90 days to assemble and one week to slide into place.

The MMRDA and J Kumar are working on it, but there are also complaints about pollution, blocked footpaths, and buildings shaking.

They are trying to fix all these problems and get more workers.

Key facts

Project Name
Sewri-Worli Connector and Elphinstone Bridge Reconstruction
Original Deadline
September 2026
New Deadline
Early 2027
Bridge Length
132 meters
Assembly Time
90 days
Sliding Time
1 week
Manpower Shortage
10-20% due to US-Iran-Israel conflict and Bengal elections

Quotes

MRIDC Official

Official from Mumbai Roads and Infrastructure Development Corporation

“All of this will take the bridge till January‑February of 2027 to be complete. Once the railway portion is ready by November, MMRDA will begin the last of the works connecting the railway and non‑railway portions. Most of the work will be done by December, leaving the finishing works for early 2027.”
indianexpress.com
“Preparation is on for the assembly and launching of the bridge’s girder over the railway tracks. These are temporary structures which will allow us to slide the girder into place. If needed, the girder will be assembled at the site before sliding. The whole process will take around 90 days.”
indianexpress.com indianexpress.com