São Paulo mayor has 19 major projects due by end of 2028
São Paulo Mayor Ricardo Nunes has 19 major public works projects scheduled for completion between October 2026 and December 2028.
Their combined cost is R$3.79 billion.
The largest is the BRT Aricanduva bus corridor, budgeted at R$647 million and due in July 2028.
Another major project, a road connection on Avenida Sena Madureira, is scheduled for December 2028.
The city’s full priority list includes 22 projects costing about R$6.7 billion, but two are due after Nunes’s term ends: road works on Estrada do M’Boi Mirim in 2029 and an avenue extension in 2030.
The timing matters because the BRT Aricanduva project is due three months before the first round of São Paulo’s 2028 municipal election.
The projects are scheduled to be completed on the dates listed, while Nunes is also seeking to support a successor in that election.
São Paulo Mayor Ricardo Nunes has 19 major public works projects scheduled for completion by December 2028.
The projects are estimated to cost a combined R$3.79 billion, according to a priorities document prepared by his team.
The largest is the BRT Aricanduva, costing R$647 million and due in July 2028.
A further three projects in the priorities agenda are scheduled for after Nunes’s term, which ends in December 2028.
- Who
- São Paulo Mayor Ricardo Nunes and his administration.
- What
- Nineteen major public works projects are scheduled for completion by the end of 2028.
- When
- From October 2026 through December 2028.
- Where
- São Paulo, Brazil.
- Why
- The projects are scheduled for delivery by the final month of Nunes’s second term.
This story does not have two clearly opposing sides.
No direct quotes in the coverage so far.
The earliest of the 19 projects is scheduled to be completed.
The Itaquera terminal, Gaivota/Ibijaú reservoir tunnel, Jurubatuba bridge and several other projects are scheduled for completion.
The final BRT Radial Leste lots, Chucri Zaidan avenue extension, Carlos Caldeira Filho avenue canalization and Grajaú bridge roadworks are scheduled for completion.
The BRT Aricanduva is scheduled to be completed.
The Sena Madureira avenue connection system is scheduled for delivery, and Nunes’s second term ends.
- Projects due by December 2028
- 19
- Estimated combined cost
- R$3.79 billion
- Largest project
- BRT Aricanduva, R$647 million
- BRT Aricanduva scheduled completion
- July 2028
- Sena Madureira avenue connection system
- R$622 million; due December 2028