Data centre installed capacity to grow by about 3x to up to 6 GW by 2030 in India: Redseer · CNBC TV 18

India is expected to build many more data centres by 2030.

Data centres are large facilities that store and process digital information.

Their total capacity could grow from about 1.65 gigawatts in 2025 to 5–6 gigawatts.

This growth is being pushed by more internet use, artificial-intelligence work and rules requiring some data to be stored locally.

Building facilities in India is also relatively inexpensive, according to the report.

The expansion will need much more electricity from the national grid.

Mumbai currently has the largest share of capacity, followed by the combined Mumbai and Chennai market.

Some AI work may move to places such as Hyderabad, the Andhra coast, Gujarat and Rajasthan because they may offer more power and land.

Key facts

Current installed capacity
About 1.65 GW in calendar year 2025
Projected 2030 capacity
5–6 GW
Estimated growth rate
27–32% CAGR across the decade from calendar year 2020
Projected 2030 grid draw
Approximately 7–9 GW
Additional grid capacity needed
Around 5 GW, compared with about 2.7 GW currently
Current geographic concentration
Mumbai has about 50% of installed capacity; Mumbai and Chennai together have about 66%
Estimated setup cost
Around USD 8 million per megawatt

Quotes

Redseer Strategy Consultants

Market research firm and author of the India Data Centres report

“Installed capacity stood at around 1.65 GW in calendar year 2025 and is expected to reach 5-6 GW by CY2030, a CAGR of 27-32 per cent across the decade from CY'20. Delivery of that trajectory requires the commissioning, within 5 years, of several times the capacity presently installed in India.”
CNBC TV 18

Sources

Related news