Officials Set Two-Month Deadline for Raptadu Water Projects

Officials Set Two-Month Deadline for Raptadu Water Projects
‘Complete drinking water supply works within 2 months’ · thehansindia.com

Officials checked how much work has been completed on village drinking-water projects.

The projects cover Atmakuru, Anantapur Rural and Raptadu mandals.

Two companies are building pipelines, tanks, filters and pumping systems.

Much of the work is still unfinished.

The officials said the remaining work must be completed within two months.

The goal is to provide water to 30 villages.

They ordered new sand filters and faster purchase of pumps.

They also asked for quicker approvals and the handover of land needed for construction.

The review was held because villages are facing water stress.

Key facts

Completion deadline
Two months for the remaining drinking-water works
Villages targeted
30 villages
Sai Pavani project
Rs 40 crore in Anantapur Rural mandal; Rs 18 crore executed and Rs 15.50 crore paid through processed bills
Saraswati Company project
Rs 50.43 crore in Atmakur; Rs 38 crore executed and Rs 34 crore paid
New sand filters
Installation ordered at a cost of Rs 60 lakh
Pipeline deadline
Remaining 350 metres to be completed within one month
Pump orders
Kirloskar pump orders to be expedited within three to four days