Allahabad High Court Upholds Interest for Delayed Flat Possession

Allahabad High Court Upholds Interest for Delayed Flat Possession
Accepting delayed flat possession does not bar homebuyer from claiming interest: Allahabad HC · theprint.in

A homebuyer paid for a flat that was supposed to be ready in 2012.

The developer offered the flat only in 2017.

The buyer accepted the flat but still asked for money because of the long delay.

The Allahabad High Court said accepting the flat did not cancel that right.

The developer said a court order about the Okhla Bird Sanctuary had stopped construction.

The High Court said the deadline had already been missed before that order began.

It also said the project’s completion and the claimed construction stoppage could not both be used as arguments.

The developer must therefore pay interest for the delayed period.

Key facts

Homebuyer
Shyam Sunder Agrawal
Developer
Antriksh Developers and Promoters Pvt Ltd
Project
Antriksh Golf View, Sector 78, Noida
Booking date
2010
Contractual possession deadline
November 2012
Actual possession offer
May 2017
Interest period and rate
December 2012 to May 2017, at one percentage point above the Marginal Cost of Fund Based Lending Rate