7 months ago

Japan Halts Nuclear Plant Screening Over Falsified Data

Japan Halts Nuclear Plant Screening Over Falsified Data
Japan's "Most Dangerous" Nuclear Plant Operator Admits That It Manipulated Earthquake Safety Data · NDTV

A big electricity company in Japan called Chubu Electric Power Co.

admitted that they changed some important safety information about their nuclear power plant.

They did this to make it seem safer during checks so they could restart two reactors.

The plant is in a very risky area for earthquakes, and experts have warned about this for a long time.

The company said they are sorry and will investigate what happened.

Because of this, the company's stock price dropped a lot.

The government wants them to explain what went wrong and how they will make sure it doesn't happen again.

The nuclear watchdog in Japan has stopped the safety checks for the reactors and will decide what to do next week.

Key facts

Company
Chubu Electric Power Co.
Location
Hamaoka Nuclear Power Plant, Shizuoka Prefecture
Issue
Manipulated earthquake safety data
Consequence
8.2% drop in shares
Investigation Deadline
April 6, 2026
Risk Level
High (87% chance of powerful earthquake)
Whistleblower Report
February 2025
Reactors Involved
No. 3 and 4
Regulator
Nuclear Regulation Authority (NRA)
Current Reactor Status
13 operational, 20 offline, 24 decommissioned

Quotes

Shinsuke Yamanaka

Chair of the Nuclear Regulation Authority (NRA)

“Ensuring safety is the first and foremost responsibility for nuclear plant operators. It is outrageous and it’s a serious challenge to safety regulation.”
republicworld.com

Sources

Related news