Sealdah Division Achieves High Train Punctuality in 2025

Sealdah Division Achieves High Train Punctuality in 2025
Sealdah division records high rate of punctuality in train running · thestatesman.com

Sealdah Division of the railway did a great job in 2025 by making trains run on time more often.

They had 95.30% of mail and express trains and 94% of suburban trains arriving on time.

This is better than the year before.

They want to make it even better in 2026 by upgrading signals at three places: Sealdah, Naihati, and Dum Dum.

They hope to finish this work by the end of March 2026 and aim for 97% punctuality next year.

Key facts

Division
Sealdah
Punctuality (Mail/Express)
95.30%
Punctuality (Suburban)
94%
Improvement (Mail/Express)
2.47%
Improvement (Suburban)
4.19%
Target for 2026
97%
Signal Upgrade Locations
Sealdah, Naihati, Dum Dum
Expected Completion Date
31 March 2026

Quotes

An official

A railway official involved in the signal upgrade project

“Of the three places, the work in Naihati is expected to be completed in February as the mandatory approval from the commissioner of railway safety has been received.”
thestatesman.com
“Next, the signal upgrade at Dum Dum would be completed. For this, the CRS has raised some compliance points which have been done and sent for an approval. At Sealdah, the task involves signal upgrade, which should not take more than four hours.”
thestatesman.com

The official

A railway official involved in the signal upgrade project

“After the upgrade of signalling, these three crucial points and some other works, we are hoping to see more improvements in punctuality percentage, particularly in the suburban section.”