Centre denies national project status to Palamuru Rangareddy lift scheme

Centre denies national project status to Palamuru Rangareddy lift scheme
PRLIS national project status put on hold · thehansindia.com

Telangana has a huge water project called the Palamuru Rangareddy Lift Irrigation Scheme.

The project is meant to lift water from the Krishna river and send it to dry farmland.

The state government asked the central government to give the project a special title called national project status.

That status can help a big project get more support and money.

But the central government said no, at least for now.

A minister named Raj Bhushan Choudhary explained that a careful technical review, called a techno-economic appraisal, must happen first.

That review cannot happen right now because there is a legal dispute between states about the Krishna river's water.

A special tribunal is hearing the dispute, and this project is part of that case.

The project's detailed report was sent for review in September 2022.

Everyone has to wait until the dispute is settled before the review can go ahead.

Key facts

Project
Palamuru Rangareddy Lift Irrigation Scheme (PRLIS)
Status sought
National project status, sought by the Telangana government
Decision
Refused by the Union Government
Reason for refusal
Techno-economic appraisal cannot currently be carried out because the matter is sub judice before the Krishna Water Disputes Tribunal-II
DPR submitted
September 2022 to the Central Water Commission
Responding minister
Raj Bhushan Choudhary, Jal Shakti Minister of State
Question raised by
Congress MP Ranuka Chauwdary in the Rajya Sabha
Appraisal authority
Central Water Commission, followed by the advisory committee on irrigation, flood control and multipurpose projects of DoWR, RD&GR

Quotes

Raj Bhushan Choudhary

Jal Shakti minister of state

“I have asked the Telangana government for the necessary details; however, as the project involves use of Krishna river waters and inter‑state aspects of the project are included in the terms of reference of the Krishna Water Disputes Tribunal‑II, the matter is now sub judice and currently the techno‑economic appraisal of the Palamuru‑Rangareddy Lift Irrigation Scheme cannot be carried out.”
thehansindia.com thehansindia.com
“A techno‑economic appraisal of the project by Central Water Commission (CWC), followed by acceptance of the project by the advisory committee on irrigation, flood control and multipurpose projects of DoWR, RD&GR is an essential pre‑requisite for further considering any project for inclusion under the ongoing schemes of this ministry.”
thehansindia.com thehansindia.com