Bombay HC Challenges MBMC Over Windsor Project Court Order

Bombay HC Challenges MBMC Over Windsor Project Court Order
Bombay HC Reprimands Mira-Bhayandar Civic Chief Over Court Order Violation, Issues Show-Cause Notice · freepressjournal.in

The Windsor project is a housing development involved in a disagreement with a city corporation.

The Bombay High Court had temporarily protected the developer from harmful official action.

The developer says MBMC still sent a notice telling it to stop construction or risk losing permission.

The developer also says this caused MahaRERA to restrict the project and freeze its bank accounts.

The judges questioned why the corporation appeared to follow a local politician’s request instead of the court’s order.

The commissioner said he did not know about the order and apologised.

The court did not immediately end the contempt matter and asked officials to explain themselves.

It also ordered MBMC and MahaRERA to reverse the specified actions.

Key facts

Case
Contempt petition filed by M/s Grandbuild Land Developers LLP
Project
Windsor, a multi-storey residential project
Court bench
Acting Chief Justice Ravindra Ghuge and Justice Gautam Ankhad
Municipal body
Mira Bhayandar Municipal Corporation
Land transferred
The developer says it transferred 1,066.42 square metres to MBMC in February 2023.
MBMC deadline
MBMC was directed to withdraw all stop-work communications within three working days.
MahaRERA deadline
MahaRERA was directed to remove adverse abeyance messages from its website within five days and unfreeze the developer’s bank accounts.

Quotes

Bombay High Court bench

The bench comprising Acting Chief Justice Ravindra Ghuge and Justice Gautam Ankhad hearing the contempt petition.

“What prompted you to obey an MLA and disobey a Division Bench order? You will obey an MLA but not a Division Bench? This is not expected..”
freepressjournal.in
“We are not accepting an apology. This is a gross case”
freepressjournal.in