Nitin Gadkari Skips Mumbai-Goa Highway Inauguration After Delays

Nitin Gadkari Skips Mumbai-Goa Highway Inauguration After Delays
Nitin Gadkari To Skip Mumbai-Goa Highway Inauguration Over 15-Year Delay · thehansindia.com

The Mumbai-Goa Highway is being widened so vehicles can travel more easily.

The work started in 2011 and was supposed to finish in 2016.

It is still not completely finished after nearly 15 years.

Road Minister Nitin Gadkari said he will not attend its opening ceremony.

Instead, he plans to drive from Mumbai to Goa in October to inspect it himself.

Some parts have potholes, traffic jams and unfinished bridges or bypasses.

The government says several problems, including land acquisition and contractor delays, slowed the project.

Gadkari says officials and contractors responsible for the delays may be punished.

Key facts

Project scope
A 485-kilometre Panvel-to-Goa/Maharashtra-border corridor is being widened from two lanes to four.
Original deadline
The project was planned for completion in 2016.
Reported progress
Parliamentary figures said 465 kilometres had been upgraded to four lanes, while Gadkari estimated overall completion at 93-94%.
Estimated cost
The expansion has cost around Rs 16,000 crore so far.
Remaining work
Bypasses, bridges and other structures remain incomplete; the Chiplun bypass is expected after the monsoon and the Mangaon bypass is set for January 2027.
Travel objective
The original plan aimed to reduce Mumbai-Goa travel time from nearly 12 hours to about six.
Current problems
Some sections have reportedly experienced potholes, puddling, road closures, repairs, traffic jams and bottlenecks.