2 days ago

Major Revamp Plans Aim to Repair Medigadda Barrage

Major Revamp Plans Aim to Repair Medigadda Barrage
Major Revamps Being Planned to Repair Medigadda Barrage · deccanchronicle.com

Officials are planning major repairs to the Medigadda barrage.

The plan includes building a bigger basin below it to help slow water when gates open.

It would also strengthen the river bed and extend the barrage’s 86 piers.

Sand must first be cleared from Medigadda and two other barrages.

Engineers are still deciding what to do with damaged Block 7.

They could strengthen it, replace it, or build a wall around it after strengthening the ground.

The designs still need to be reviewed by the Central Water Commission.

Officials say the work may take at least a year, while the government hopes it will be done before the 2027 monsoon.

Key facts

Project
Kaleshwaram Lift Irrigation Scheme
Proposed basin
An extended stilling basin on the downstream side
Piers
All 86 would be extended to the edge of the proposed stilling basin
Other proposed measures
Two cut-off walls, an extended upstream raft, and ground strengthening by grouting
Preparatory work
Sand accumulation at the barrages is reported to be three to five metres deep in some places
Block 7
Options include strengthening the existing block, removing and rebuilding it, or building a blocking wall after strengthening the ground
Estimated duration
At least one year, if preparatory requirements proceed quickly
Approval
The designs are to be submitted to the Central Water Commission for vetting

Quotes

Source involved with repair-plan discussions

A source involved in discussions on the repair plans.

“There is still uncertainty on the way forward as far as Block 7 is concerned, whether to repair it, build a new one, or build a blocking wall around it after strengthening the ground under the block and its adjacent blocks.”
deccanchronicle.com
“The required works are expected to be complex. Some components constitute huge additions, such as building a new extended stilling basin on the downstream side to ensure that problems of the past do not recur.”
deccanchronicle.com

Irrigation department official

An official of the irrigation department.

“The designs are robust with measures to address every concern plaguing the barrages. Once completed, the barrages should stand strong.”
deccanchronicle.com

Sources

Related news