World Bank says Lebanon is slow to use reconstruction aid
Lebanon has been slow to use international aid to rebuild areas damaged in its wars with Israel.
The World Bank approved $250 million in June 2025 to clear rubble and repair public infrastructure damaged in the 2024 war.
By September, just $4.2 million had been paid out, well below the $100 million expected by July 2026.
World Bank official Anna Bjerde said security problems and overstretched institutions were slowing work and making it difficult to decide where repairs could safely begin.
Lebanon’s government says delayed parliamentary approval and worsening security held up the projects.
The World Bank estimates rebuilding after the 2024 war will cost about $11 billion, while fighting that resumed in March 2026 caused further damage.
Lebanon says projects worth $70 million are expected to launch by the end of 2026.
The World Bank says Lebanon has been slow to use international aid for reconstruction after wars with Israel.
A September progress report showed that only $4.2 million of a $250 million World Bank loan had been paid out.
The loan was approved in June 2025 to clear rubble and repair damaged public infrastructure.
Lebanon’s government says delays in parliamentary ratification and worsening security held up the start of projects.
The World Bank estimates that rebuilding after the 2024 war would cost about $11 billion.
- Who
- The World Bank and the Lebanese government. World Bank managing director of operations Anna Bjerde discussed the pace of reconstruction.
- What
- Lebanon has been slow to use international aid to rebuild areas damaged in recent wars.
- When
- Bjerde spoke during a visit to Lebanon on Tuesday; the articles were published on November 18, 2026.
- Where
- Lebanon, including war-damaged areas in the south.
- Why
- The World Bank cited slow progress, overstretched institutions and security concerns. Lebanon’s government also cited delays in parliamentary ratification and worsening security.
World Bank
Lebanese government
Reason for delays
World Bank
The World Bank cited overstretched institutions and security issues requiring careful planning.
Lebanese government
The government said parliamentary ratification of the loan was delayed and worsening security held up project activities.
Progress
World Bank
The World Bank said aid was being used more slowly than it wanted and called for work to move faster.
Lebanese government
The government said its Council for Development and Reconstruction had taken steps to speed up implementation.
The World Bank approved a $250 million loan to help clear rubble and repair damaged public infrastructure.
A progress report showed that $4.2 million had been paid out.
Anna Bjerde discussed the pace of reconstruction during a visit to Lebanon, including visits to damaged areas in the south.
The articles reporting the slow use of reconstruction aid were published.
- World Bank loan
- $250 million, approved in June 2025
- Paid out
- $4.2 million as of the September progress report
- Initial disbursement projection
- $100 million by July 2026
- Estimated reconstruction cost
- About $11 billion after the 2024 war
- Expected projects
- $70 million worth of projects expected to launch by the end of 2026
3 sources
What people are saying
I think we have to be honest and say it’s slower than where we want it to be
institutions in Lebanon are very thinly stretched
because you cannot let the people down
Parliament ratification of the said loan experienced considerable delays and the worsening security situation due to the conflict with Israel delayed the timely launch of project activities.