Delhi-Mumbai Expressway’s nonstop drive may wait until December 2029

Delhi-Mumbai Expressway’s nonstop drive may wait until December 2029

The Delhi-Mumbai Expressway may not offer a nonstop drive until December 2029.

Three sections covering about 90 kilometres in Gujarat have not yet started construction.

The contracts were terminated after the original developer, Roadways Solutions India Infra Ltd, failed to meet project milestones despite extensions.

NHAI is evaluating bids for two sections and selecting a replacement contractor for the third.

One earlier bidder did not sign its contract and gave up Rs 15 crore in bid security.

NHAI hopes to finish the appointment process this month, start work within a couple of months and complete the three sections in about two years.

Sections in Maharashtra and Rajasthan are expected by April 2027, while the Gujarat sections could follow by December 2029.

The expressway was intended to cut Delhi-Mumbai travel time by half, to about 12 hours.

1 source

Related

What people are saying

Unnamed NHAI officialOfficial involved in the project
These three stretches would be ready latest by December 2029. The Expressway project has faced delay due to several reasons, including Covid-19, delay in land acquisition and statutory approvals.
via Times of India