Politics · Spain · 4 hrs ago
Adif contract for Extremadura rail line rose 15% after award
A joint venture formed by Azvi and Sevilla Nevado won an Adif contract for a high-speed rail project in Extremadura in 2019.
The project covers a section of the Madrid-to-Extremadura line near Mérida.
After work began, Adif approved a change that raised the contract from €28.27 million to €32.66 million, an increase of about 15%.
The deadline was also extended by 10 months, from 24 months to 34.
Spain’s Civil Guard says its investigation found signs of a potentially irregular award, including messages in which former driver Cristian Corvillo sought help from Koldo García for the companies.
Adif officials from that period deny wrongdoing and say the award followed technical reports; the investigation is examining the case.
Adif raised the price of a rail construction contract in Extremadura by 15% after awarding it to a joint venture of Azvi and Sevilla Nevado.
The contract rose from €28.27 million to €32.66 million, an increase of about €4.4 million.
The change, approved in August 2022, also extended the construction period by 10 months beyond the original 24 months.
Spain’s Civil Guard says its investigation found indications of irregularities in the 2019 award.
Adif officials from the time deny irregularities and say the award followed technical reports.
- Who
- Adif and the Azvi-Sevilla Nevado joint venture. The Civil Guard’s Central Operational Unit is investigating the award.
- What
- Adif increased the contract price by 15% after the contract was awarded.
- When
- The contract was awarded in 2019; the price change was approved in August 2022.
- Where
- The Madrid-Extremadura high-speed rail line, on the San Rafael–Cuarto de la Jara section near Mérida.
- Why
- Adif said the change was needed because of circumstances a diligent contracting authority could not foresee. The article also cites cost increases following Russia’s invasion of Ukraine.
Adif officials from the time
Spain’s Civil Guard’s Central Operational Unit
Irregularities
Adif officials from the time
Officials deny irregularities and say the award followed technical reports.
Spain’s Civil Guard’s Central Operational Unit
The unit’s report to a judge cites indications of an irregular award.
Contract change
Adif officials from the time
Adif attributed the change to unforeseen circumstances.
Spain’s Civil Guard’s Central Operational Unit
The article reports the 15% increase as one of several concerning indications in the case.
Adif awarded the construction contract to the Azvi-Sevilla Nevado joint venture.
Adif approved a change that raised the contract price to €32.66 million and extended the completion period by 10 months.
The Civil Guard’s Central Operational Unit obtained the file from Adif and the two construction companies.
- Initial contract value
- €28.27 million
- Revised contract value
- €32.66 million
- Price increase
- 15%, or about €4.4 million
- Original construction period
- 24 months
- Revised construction period
- 34 months
- Rail section
- San Rafael–Cuarto de la Jara, near Mérida
What people are saying
the overall conception of the work is considered complete, detailed and coherent, and the justification of the work execution methodology is fully developed and has a very good level of coherence
need for modification arising from circumstances that a diligent contracting authority cannot foresee
acted in accordance with the technical reports