Yotta Data Services secured a ₹2,948-crore loan from state-owned lender IIFCL to build a data centre in Noida.
The 15-year loan will help fund a project expected to cost ₹3,879 crore and add 61 megawatts of data processing capacity.
Promoter Darshan Hiranandani must eventually buy the Nvidia GPUs that Yotta will initially rent for the facility.
The loan terms allow IIFCL to seize the chips if Yotta fails to make payments.
The final 20% of the loan depends on Yotta showing it has clients for the data centre.
Yotta’s total long-term borrowings now stand at ₹13,488 crore, or more than $1.4 billion.
The loan adds to concerns about Yotta’s rising debt, which credit rating agencies have flagged as the company expands its data centre business.
Yotta’s promoter, Darshan Hiranandani, must eventually buy the Nvidia GPUs used at its Noida data centre under conditions attached to a ₹2,948-crore loan from state-owned IIFCL.
The chips will initially be rented for AI workloads from London-based Gorilla Technology Group.
The loan document also requires Hiranandani to cover any shortfall in the cost of buying an equivalent quantity of GPUs.
IIFCL can seize the chips if Yotta defaults, and Yotta must provide proof of customer agreements to receive the final 20% of the loan.
The loan will help fund a data centre project with an estimated cost of ₹3,879 crore and is expected to add 61 MW of data processing capacity.
- Who
- Yotta Data Services, its promoter Darshan Hiranandani, and state-owned lender IIFCL.
- What
- IIFCL’s loan terms require Hiranandani to buy the Nvidia GPUs used at Yotta’s Noida data centre and cover any shortfall in the purchase cost.
- When
- The loan document is dated 9 September. The article was published on 16 November 2026.
- Where
- Yotta’s D2 data centre in Noida, India.
- Why
- The loan conditions require the promoter to own the GPUs and allow IIFCL to seize them if Yotta defaults.
This story does not have two clearly opposing sides.
The IIFCL loan document set out the conditions requiring the promoter to buy the GPUs and cover any shortfall.
Mint reported that Yotta had secured the ₹2,948-crore IIFCL loan for its Noida data centre.
- IIFCL loan
- ₹2,948 crore ($315 million)
- Project cost
- ₹3,879 crore
- Promoter contribution
- ₹931 crore
- Data centre capacity
- 61 MW
- Yotta long-term borrowings
- ₹13,488 crore (over $1.4 billion)
What people are saying
milestone-linked disbursement is the standard architecture of infrastructure lending in India: funds are released as the project is built and as the arrangements that will generate its revenue are put in place.
Aligning the final tranche with the deployment arrangements for the facility's GPU capacity is a prudent structure that Yotta welcomes.
Weighted average debt tenure in excess of 10 years is long as against the shorter contract tenure and lifespan for GPU business remains a risk and requires monitoring