Business · Economy · 14 hrs ago
Saudi Construction Tender Price Inflation Forecast to Reach 5% in 2026
JLL expects Saudi construction tender price inflation to reach 5% in 2026, up from its earlier forecast of 4%, and remain at that rate in 2027.
Higher material costs and supply disruptions are driving the rise in a market affected by geopolitical tensions and regional trade delays.
Copper prices were up 44.5%, aluminum 23.9% and diesel 7.9% by August, adding to the cost of projects that rely on metals and imported materials.
Delays in supplies are raising project schedule risks, while competition has led contractors to absorb some cost increases by accepting lower profit margins.
The construction sector is expected to grow moderately and steadily in 2026 and 2027, after years of rapid expansion.
In Riyadh, changes to fees on undeveloped land have helped increase the supply of land for development and ease price pressure.
Public-private projects in health, education and urban development continue to attract companies, helping sustain activity in the sector.
JLL forecasts Saudi Arabia’s construction tender price inflation will reach 5% in 2026, up from its previous forecast of 4%.
It expects the rate to remain at 5% in 2027.
Higher construction material costs and supply chain disruptions are driving the forecast increase.
Geopolitical tensions and regional trade disruptions have delayed deliveries of construction materials and equipment.
JLL expects moderate, stable growth in Saudi Arabia’s construction sector in 2026 and 2027.
- Who
- JLL made the forecast in its report on Saudi Arabia’s construction market.
- What
- Construction tender price inflation is forecast to reach 5% in 2026 and remain at that level in 2027.
- When
- The forecast covers 2026 and 2027.
- Where
- Saudi Arabia.
- Why
- Rising material costs and supply chain disruptions are driving the increase.
This story does not have two clearly opposing sides.
Copper prices were up 44.5%, aluminum 23.9% and diesel 7.9% as of August, according to JLL.
JLL forecast construction tender price inflation of 5%, revising its previous forecast of 4%.
JLL expects tender price inflation to remain at 5%.
- 2026 tender price inflation forecast
- 5%
- Previous forecast
- 4%
- 2027 tender price inflation forecast
- 5%
- Copper price increase
- 44.5% as of August
- Aluminum price increase
- 23.9% as of August
- Diesel price increase
- 7.9% as of August