Karian-Serpong water pipeline project reaches 33.77% completion
WIKA’s Karian-Serpong pipeline project is 33.77% complete as of mid-November 2026.
The project involves an 18-kilometre pipeline section being built by a consortium led by Indonesian state-owned construction company WIKA.
It will carry raw water from Karian Dam in Banten to Banten, Jakarta and parts of West Java.
The system is designed to carry about six cubic metres of water per second.
Once operating, it is expected to support 1.3 million new household water connections, reaching about 5.2 million people and reducing reliance on groundwater.
The project is targeted for completion on 3 August 2027, with the system planned to start operating in 2028.
The next step is to finish construction and quality checks on the pipeline.
The Karian-Serpong Conveyance System Package 3 had reached 33.77% completion by mid-November 2026.
A WIKA-led consortium is building about 18 kilometres of raw-water pipeline for the project.
The system will carry water from Karian Dam in Banten to areas of Banten, Jakarta and parts of West Java.
It is planned to begin operating in 2028 and is expected to provide about 1.3 million new drinking-water connections for roughly 5.2 million people.
Package 3 is targeted for completion on 3 August 2027.
- Who
- PT Wijaya Karya (WIKA), through the WIKA-NK-Jaya Konstruksi-Daeah JV consortium, is building Package 3.
- What
- The package is an approximately 18-kilometre raw-water pipeline project. It had reached 33.77% completion by mid-November 2026.
- When
- The progress figure was reported for mid-November 2026. Completion is targeted for 3 August 2027.
- Where
- The system carries water from Karian Dam in Lebak Regency, Banten, to Banten, Jakarta and parts of West Java.
- Why
- The system is intended to provide piped drinking water, reduce reliance on groundwater and support urban and industrial growth.
This story does not have two clearly opposing sides.
Package 3 had reached 33.77% completion, with 584 pipe sections laid out and 410 joints welded.
CNBC Indonesia reported the project's progress.
Package 3 is targeted for completion.
The system is planned to begin operating.
- Progress
- 33.77% by mid-November 2026
- Pipeline length
- About 18 kilometres
- Water source
- Karian Dam, Lebak Regency, Banten
- Capacity
- About 6 cubic metres per second
- Target completion
- 3 August 2027
- Planned operation
- 2028
What people are saying
Every joint is carried out under strict procedures because its quality determines the reliability of the entire network. Work safety is also a priority at every stage.
We hope KSCS can provide more reliable piped drinking-water services for people in Banten, Jakarta and surrounding areas, and support the growth of urban and industrial areas.